Purchasing Type: Change Order (CO)
Public Hearing: YES ? NO ? Department: Purchasing & Contracting
AGENDA ITEM:
Title
Commission District(s): All
CO - Change Order No. 2 to Contract No. 1081070 Design Build Services for Gravity Sewer System Rehabilitation Replacement & Construction - Package No. 2 (Multiyear): for use by the Department of Watershed Management (DWM). This contract consists of design build services to perform pipe rehabilitation or upsizing to the gravity sewer system. This request is to increase the scope of work, funding, and the contract term through June 30, 2022 to allow for the completion of work. Awarded to Granite Inliner, LLC. Amount Not To Exceed: $4,022,536.05.
Body
Information Contact: Cathryn G. Horner, Director
Phone Number: (404) 371-6334
PURPOSE:
Awarded by the BOC on April 11, 2017 for an amount not to exceed $26,892,824.98. On June 9, 2020, the BOC approved Change Order No. 1 to extend the contract term to June 30, 2021. This contract's design build services primarily include assessments using CCTV and/or TISCIT, cured-in-place pipe lining, pipe and/or manhole point repairs, pipe replacements utilizing either open-cut or pipe-bursting methods, and manhole rehabilitation and/or replacement. This change order request is initiated to accommodate Owner initiated changes due to updated sewer capacity requirements and sewer realignments caused by easement acquisition negotiations. This request to increase the scope of work, funding, and the contract term will allow the Contractor the ability to continue project completion by adding flow capacity to the County's Sanitary Sewer System in order to minimize sewer spills.
RECOMMENDATION:
Recommended Action
Recommend approval of Change Order No. 2 with:
Granite Inliner, LLC, 2090 Tucker Industrial Road, Suite A-1, Tucker, GA 30017
Amount Not To Exceed: $4,022,536.05
and authorize the Chief Execu...