File #: 2023-0125    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 1/20/2023 In control: PWI-Public Works & Infrastructure Committee
On agenda: 2/7/2023 Final action: 2/16/2023
Title: Commission District(s): 5 & 7 Agreement for the Construction and Financing of Sewer Upgrades with Hidden Hills Condo LLC Not to Exceed $291,000 for Phase 1 and $190,500 for Phase 2.
Attachments: 1. 5083 Biffle Rd - Terra Bella (Hidden Hills) Agreement 11.1.22 final

                                    

Public Hearing:  YES      NO                                                   Department: Watershed Management                                     

 

SUBJECT:

Title

Commission District(s): 5 & 7

Agreement for the Construction and Financing of Sewer Upgrades with Hidden Hills Condo LLC

Not to Exceed $291,000 for Phase 1 and $190,500 for Phase 2.

Body

 

Information Contact: David Hayes

Phone Number: 770-414-6240

 

PURPOSE:

To consider approving an agreement for the Construction and Financing of Sewer Upgrades in
the Snapfinger model shed with Hidden Hills Condo LLC.

 

NEED/IMPACT:

Hidden Hills Condo LLC seeks to construct and offering 397 housing units at 5083 Biffle Road,

Stone Mountain, GA, 30088, (the “Project”) and the Project requires upgrading and expanding

portions of the existing sanitary sewer infrastructure and lines to accommodate additional

discharge of wastewater into the Sewer System. The purpose of this Agreement is for the parties

to enter a binding contract evidencing their agreement as to the installation and financing of the

improvements for this development.

This development exceeds the maximum participation peak flow rate to receive County generated

credits, per the County policy for allocating wastewater capacity credits, hence the

company will participate in the completion of capacity credit generation. The improvements

will consist of upgrades and expansion of certain portions of the DeKalb County sanitary sewer

infrastructure and lines servicing the Snapfinger model shed. The improvements will allow for

a total of 397 residences. The County, through its Department of Watershed Management

and/or its contractor, will determine those portions of the sanitary sewer infrastructure and lines

to be upgraded and expanded (the “Work”). The Work will be divided into two phases. The

first portion of the improvements will be completed no later than February 1, 2024. The

remainder of the improvements will be completed by September 1, 2024. Completed

improvements shall generate 220,335 gallons per day in sewer capacity credits as calculated per

DeKalb County’s Capacity Assurance Banking Credit Program. Company agrees that upon

completion of each phase of the improvements and before Company shall be allowed access to

the County’s sanitary sewer system, Company shall reimburse the County up to $291,000 for

the first portion of the project (delivering 133,200 gallons per day of credit) and up to $190,500

for the second portion of the project (delivering 87,135 gallons per day of credit) for up to

$481,500 combined of the estimated total cost of $963,000 for sewer improvements in the

Snapfinger model shed. (“Company’s Contribution”).

 

FISCAL IMPACT:

The County's contribution is not anticipated to exceed $481,500

 

RECOMMENDATION:

Recommended Action

To authorize the CEO or designee to execute the Agreement and all necessary documents in a form acceptable to the County Attorney.