File #: 2023-1511    Version: 1 Name:
Type: Resolution Status: Action
File created: 11/15/2023 In control: Board of Commissioners
On agenda: 12/19/2023 Final action: 12/18/2023
Title: Commission District(s): 4 and 7 One (1) year extension of the term of the Agreement for Construction and Financing of Sewer Upgrades (the "Agreement") dated June 23, 2023 by and between DeKalb County, Georgia (the "County") and Captura Rockbridge Acquisition, LLC (the "Company"), including a one (1) year extension of the County's approval of Company's request for sewer capacity.
Attachments: 1. 2023.10.6 - Request for Extension - SIGNED, 2. 2023.11.1 - Request for BOC Approval - SIGNED, 3. 2023.6.23 - Agreement for Construction Financing of Sewer Upgrades - EXECUTED

                                    

Public Hearing:  YES      NO                                                   Department: Watershed Management                                     

 

SUBJECT:

Title

Commission District(s): 4 and 7

One (1) year extension of the term of the Agreement for Construction and Financing of Sewer Upgrades (the “Agreement”) dated June 23, 2023 by and between DeKalb County, Georgia (the “County”) and Captura Rockbridge Acquisition, LLC (the “Company”), including a one (1) year extension of the County’s approval of Company’s request for sewer capacity.

Body

 

Information Contact: David Hayes

Phone Number: 770-414-6240

 

PURPOSE:

The Company is undertaking the construction of seventy-eight (78) single-family homes located at 4962, 4964, 4994, and 5046 Rockbridge Road, Stone Mountain, GA 30008 (the “Project”). The Project will require upgrading and expanding portions of the existing sanitary sewer infrastructure lines to accommodate additional discharge of water into the Sewer System (the “Improvements”). Pursuant to the Agreement, the County’s Department of Watershed Management and its contractors completed the Improvements. The Company is to contribute to the County the monetary amount of Ninety-Five Thousand and No/100 Dollars ($95,000.00) as the appropriate method of cost sharing upon completion of the Improvements and before the Company shall be allowed access to the County’s sanitary sewer system as set forth in the Agreement (the “Company Contribution”).

 

NEED/IMPACT:

The Company has in good faith diligently proceeded with the necessary entitlements in order to develop the Project. Currently, the Project is still in the lot combination and plat consolidation phase. The Company will still need to proceed with and complete a sketch plat review and approval prior to being in a position to seek land disturbance permits and commence the upgrades and expansion of the existing sanitary sewer infrastructure and lines set forth in the Agreement.

 

FISCAL IMPACT:

Delay of payment of the Company Contribution to the County.

 

RECOMMENDATION:

Recommended Action

To authorize the CEO or designee to execute all necessary documents in a form acceptable to the County Attorney.