Legislation Details

File #: 2026-1041    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 6/2/2026 In control: Board of Commissioners
On agenda: 7/14/2026 Final action:
Title: Commission District(s): All CO - Change Order No. 5 to Contract No. 1258006 Stormwater Master Plan. For use by Public-Works - Roads and Drainage (R&D) to provide stormwater master planning services. Seeking increase in contract funds, scope of services, and term through June 30, 2028. Awarded to Arcadis US, Inc: Amount Not To Exceed: $2,299,900.00.
Attachments: 1. Agenda Notes, 2. Change Order Request Form
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): All

CO - Change Order No. 5 to Contract No. 1258006 Stormwater Master Plan. For use by Public-Works - Roads and Drainage (R&D) to provide stormwater master planning services. Seeking increase in contract funds, scope of services, and term through June 30, 2028. Awarded to Arcadis US, Inc: Amount Not To Exceed: $2,299,900.00.

Body

 

Information Contact: Michelle Butler, Chief Procurement Officer

Phone Number: (404) 687-3581

 

PURPOSE:

Awarded by the BOC on June 22, 2021, for an amount not to exceed $572,180.00. On December 13, 2022, the BOC approved Change Order No. 1 to increase the contract term through July 31, 2023. On December 12, 2023, the BOC approved Change Order No. 2 to ratify a previously provided six (6) month contract term increase and increase the contract funds, scope of services and term through December 31, 2024. On October 22, 2024, the BOC approved Change Order No. 3 to increase the contract term through December 31, 2025, and to add certified LSBE-DeKalb vendor, Accura Engineering and Consulting Services Inc. On October 28, 2025, the BOC approved Change Order No. 4 to increase the contract funds, scope of services and term through June 30, 2027. This request is to add an additional scope of work, increase the contract term through March 28, 2028, and increase contract funds for an amount not to exceed $2,299,900.00.  The extension will allow the contractor additional time to complete the added scope for both the South River and Yellow River Watershed Phase III Stormwater Master Plan, as well as provide the time and funding needed for completion.

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 5 with:

 

Arcadis US, Inc., 2839 Paces Ferry Road, Suite 900, Atlanta, Georgia, 30339

 

Amount Not To Exceed: $2,299,900.00

 

and authorize the Chief Executive Officer to execute the change orders and all associated documents

 

ADDITIONAL INFORMATION:

1. LSBE Participation                                                               27%

2. Contract Effective Date:                                          December 27, 2021

3. Contract Expiration Date:                                           June 30, 2027

4. Amount Spent to Date:                                           $598,442.23                     

5. Funding:                                                                                     Stormwater Management Operating (R&D)