Legislation Details

File #: 2026-1557    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 10/20/2026 In control: Board of Commissioners
On agenda: 12/8/2026 Final action:
Title: Commission District(s): 3 and 7 CO – Change Order No. 8 to Contract No. 13-902684 Snapfinger Creek AWTP Expansion – Phase II Construction Management (CM) Services. For use by the Department of Watershed Management (DWM) to obtain CM services. This request seeks to extend the contract term through August 31, 2027. Awarded to Tetra Tech, Inc. INCREASE CONTRACT TERM ONLY.
Attachments: 1. Agenda Note, 2. UD CO#8 Request form
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES ☐     NO ☒                                  Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): 3 and 7

CO - Change Order No. 8 to Contract No. 13-902684 Snapfinger Creek AWTP Expansion - Phase II Construction Management (CM) Services. For use by the Department of Watershed Management (DWM) to obtain CM services. This request seeks to extend the contract term through August 31, 2027. Awarded to Tetra Tech, Inc. INCREASE CONTRACT TERM ONLY.

Body

 

Information Contact: Michelle Butler, Chief Procurement Officer

Phone Number: (404) 687-3581

 

PURPOSE:

Awarded by the BOC on July 16, 2013, for an amount not to exceed $10,278,218.00. On December 13, 2016, the BOC approved Change Order No. 1 to increase the contract term to December 31, 2021, and funding in an amount not to exceed $7,221,351.53. On December 17, 2019, the BOC approved Change Order No. 2 authorizing overtime work up to an estimated $448,000.00 using existing contract funds. On August 25, 2020, the BOC approved Change Order No. 3 to increase the contract term to June 30, 2022, and funding in an amount not to exceed $9,162,850.00. On June 14, 2022, the BOC approved Change Order No. 4 to increase the contract term to November 30, 2023. On June 27, 2023, the BOC approved Change Order No. 5 to increase the contract term to December 31, 2024, and funding in an amount not to exceed $2,781,477.40. On December 10, 2024, the BOC approved Change Order No. 6 to increase the contract term to December 31, 2025 and funding in an amount not to exceed $1,500,000.00. On July 14, 2026 the BOC approved Change Order No. 7 to increase the contract term to December 31, 2026, and funding in an amount not to exceed $654,042.00.

This contract consists of the provision of various construction management services, to include pre-construction services; construction inspection and other field services; progress meetings; contractor submittal review; construction safety plan review; construction change order reviews and final inspections; and project close out. This request to extend Tetra Tech’s contract term is for the purpose of aligning with the ongoing construction completion schedule established in the Phase 2 Contract with Archer Western Construction, LLC. The Contractor (Archer Western Construction, LLC) did not complete the project prior to Tetra Tech’s existing construction management contract expiration date of December 31, 2025. Allowing the extension until August 31, 2027 will permit the continuation of management services relating to close-out of the project and as-needed for mediation support services through Final Completion. Not approving this request could result in delays from the contractor as construction management services are required while the contractor is working to ensure Work performed meets contractual requirements.

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 8 with:

 

Tetra Tech, Inc., 280 Interstate North Circle, Suite 300, Atlanta, GA 30339

 

and authorize the Chief Executive Officer to execute the change order and all associated documents.

 

 

ADDITIONAL INFORMATION:

1.                     LSBE Participation:                                          28.23%

2. Contract Effective Date:                                          August 7, 2013

3. Contract Expiration Date:                                          December 31, 2026

4. Amount Spent to Date:                                          $30,933,598.49

5. Funding:                                                                                    Renewal and Enterprise and/or Bond