Legislation Details

File #: 2026-0951    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 5/22/2026 In control: Board of Commissioners
On agenda: 6/23/2026 Final action:
Title: Commission District(s): 1,4,6,7 RFQ - Request for Qualifications (RFQ) 2025-038-RFQ Design Services for North Fork Peachtree Creek Trail from Fisher Trail to Chamblee Tucker Road (PI#0020668). For use by Public Works - Transportation (PW-T) to obtain design services for North Fork Peachtree Creek Trail. Recommend award to the highest scoring proposer: Thomas & Hutton Engineering Co.: Amount Not To Exceed: $998,946.59.
Attachments: 1. Agenda Notes, 2. UD Rec Form - SPLOST, 3. Cumulative Score Report - Fork, 4. Summary Comments
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Purchasing Type: Request for Proposals (RFP)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): 1,4,6,7

RFQ - Request for Qualifications (RFQ) 2025-038-RFQ Design Services for North Fork Peachtree Creek Trail from Fisher Trail to Chamblee Tucker Road (PI#0020668).  For use by Public Works - Transportation (PW-T) to obtain design services for North Fork Peachtree Creek Trail.  Recommend award to the highest scoring proposer: Thomas & Hutton Engineering Co.: Amount Not To Exceed: $998,946.59.

Body

 

Information Contact: Michelle Butler, Chief Procurement Officer

Phone Number: (404) 687-3581

 

PURPOSE:

Consists of the preparation of a scoping study for this trail segment that will include the development of a limited-scope concept report from Fisher Trail Park to Chamblee Tucker Road along North Fork Peachtree Creek.  Five (5) proposals were received.

 

RECOMMENDATION:

Recommended Action

Recommend award to the highest ranked proposer:

 

Thomas & Hutton Engineering Co., 50 Park of Commerce Way, Savannah, GA 31405

 

Amount Not To Exceed: $998,946.59

 

and authorize the Chief Executive Officer to execute the contract and all associated documents.

 

Evaluation Committee Scores:

 

Firm/Phase:                                                                                                                                                   Scores:

Thomas & Hutton Engineering Co.                                                                                    950

American Engineers, Inc dba STV Services                                                               675

Kimely-Horn & Associates                                                                                                         850

 

After evaluation of technical proposals, the recommendation is to award to the highest scoring proposer.

 

ADDITIONAL INFORMATION:

1. Contract Effective Date:                                                               Contract Execution Date

2. Contract Expiration Date:                                                               December 31, 2032

3. Funding:                                                                                                         $799,157.27 - Federal (GDOT)

                                                                                                                              $199,789.32 - SPLOST

4. Additional Bidders:

 

EFK Moen

2300 Windy Ridge Pkwy, SE

Ste 210S

Atlanta, GA  30339

(Non-Responsive)

 

American Engineers, Inc. dba STV Services

5160 Acworth Landing Drive

Acworth, GA 30101

 

BCC Engineering, LLC d/b/a Heath & Lineback

2390 Canton Road, Bldg. 200

Marietta, GA 30066

(Non-Responsive)

 

Kimley-Horn and Associates, Inc.

3930 East Jones Bridge Road

Suite 350

Peachtree Corners, GA 30092