File #: 2025-1198    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 8/14/2025 In control: Board of Commissioners
On agenda: 9/23/2025 Final action:
Title: Commission District(s): All CO - Change Order No. 3 to Contract No. 1379287, Juvenile Justice Center Canopy Installation (180 Day Contract): for use by the Department of Facilities Management (FM). This contract consists of construction services for the installation of a canopy over the Judges' parking lot at the DeKalb County Juvenile Justice Center. This request seeks to ratify a previously provided contract term increase. This request also seeks to extend the contract term through December 31, 2025. Awarded to: Brad Construction Company II, LLC. Amount Not To Exceed: $20,274.58.
Attachments: 1. 2025-1198, Agenda Notes, 2. User Department Change Order Form
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): All

CO - Change Order No. 3 to Contract No. 1379287, Juvenile Justice Center Canopy Installation (180 Day Contract): for use by the Department of Facilities Management (FM). This contract consists of construction services for the installation of a canopy over the Judges’ parking lot at the DeKalb County Juvenile Justice Center. This request seeks to ratify a previously provided contract term increase.  This request also seeks to extend the contract term through December 31, 2025. Awarded to: Brad Construction Company II, LLC. Amount Not To Exceed: $20,274.58.

Body

 

Information Contact: Michelle Butler, Chief Procurement Officer

Phone Number: (404) 687-3581

 

PURPOSE:

Awarded by the BOC, on May 28, 2024 for an amount not to exceed $443,831.19.  On October 8, 2024, the BOC approved Change Order No. 1 notating a revised contract term of May 31, 2025 to allow the vendor appropriate time to complete from the recission and re-award of this project.  On May 29, 2025, the BOC approved Change Order No. 2 extending the contract term through August 31, 2025 due to delays in the manufacturing of the pre-fabricated building.  This contract consists of the installation of a canopy over the Judges’ parking lot at the DeKalb County Juvenile Justice Center. This request seeks to ratify a previously provided contract term increase.  This request also seeks to extend the contract term through December 31, 2025 and to increase funding in the amount of $20,274.58 for unforeseen conditions that arose during the construction.

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 3 with:

 

Brad Construction Company II, LLC, 500 W. Lanier Ave., Fayetteville, GA 30214

 

Amount Not To Exceed: $20,274.58

 

and authorize the Chief Executive Officer to execute the change order and all associated documents.

 

ADDITIONAL INFORMATION:

1. LSBE Participation:                                                               LSBE-MSA Firm

2. Contract Effective Date:                                                               September 19, 2024

3. Contract Expiration Date:                                                               October 15, 2025

4. Amount Spent To Date:                                                               $267,305.43

5. Funding:                                                                                                         CIP (FM)