Title: Commission District(s): 1 & 6 Water Utility Installation for Upcoming City of Dunwoody Project Cost to the County: Not To Exceed $400,600
Attachments: 1. 2018 06.12 Item 2018-2250.pdf

                                    

Public Hearing:  YES      NO                                                   Department: Watershed Management                                     

 

SUBJECT:

Title

Commission District(s): 1 & 6

Water Utility Installation for Upcoming City of Dunwoody Project

Cost to the County:  Not To Exceed $400,600

 

Body

Information Contact: Reginald Wells, Interim Director, Watershed Management

Phone Number: 770-621-7208

 

PURPOSE:

To authorize payment to the City of Dunwoody (COD) per the approved Intergovernmental Agreement (IGA) in the amount not to exceed the following listed amount, for the water installation and adjustments associated with the following project; and to authorize the Chief Executive Officer (CEO) to execute an agreement allowing for the payments and to execute all necessary documents to complete this transaction.

            Mount Vernon Road at Vermack Road Intersection Improvements (not to exceed $400,600)

 

NEED/IMPACT:

The COD project, Mount Vernon Road at Vermack Road Intersection Improvement project is scheduled to begin construction in June 2018.  The project consists of the roadway widening of approximately 0.30 miles, drainage improvements, sidewalk construction, waterline installation, milling and paving on Mount Vernon Road between Vernon Oaks Drive and Corners Drive.  The Department of Watershed Management (DWM) will provide funding and oversight to COD for the waterline replacement of the existing six (6) inch and twelve (12) inch waterline portion of the project.

 

It is important to both DWM and COD to include the waterline installation on major roadway projects to ensure the work is performing concurrently.  This minimizes the impact to adjacent property owners and the traveling public.  In order to include the installation in the COD’s roadway construction contract, DWM must agree to pay the listed cost of completing the work.

 

Watershed concurs with City of Dunwoody award to CMES as the lowest overall responsive, responsible bidder for this joint city/county project per the IGA, and includes a good faith effort at LSBE participation.

 

 

FISCAL IMPACT:

Cost to the County not to exceed $400,600

 

RECOMMENDATION:

Recommended Action

Authorize payment to the City of Dunwoody in amount not to exceed the following listed amount, for water installation and adjustments associated with the following projects; and to authorize the Chief Executive Officer to execute an agreement allowing for these payments and to execute all necessary documents to complete these transactions:  Mount Vernon Road & Vermack Road Intersection Improvements (not to exceed $400,600).