Skip to main content
File #: 2025-0493    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 3/26/2025 In control: PWI-Public Works & Infrastructure Committee
On agenda: 5/6/2025 Final action:
Title: Commission District(s): 4 & 7 Agreement for the Construction and Financing of Sewer Upgrades with AERDNA, LLC with a contribution of $256,500.00.
Attachments: 1. Cost Sharing Agreement-Juniper Heights 3563 Bishop Dr-03212025

                                    

Public Hearing:  YES      NO                                                   Department: Watershed Management                                     

 

SUBJECT:

Title

Commission District(s): 4 & 7

Agreement for the Construction and Financing of Sewer Upgrades with AERDNA, LLC with a contribution of $256,500.00.

Body

 

Information Contact: Reginald Wells, Director

Phone Number: 770-414-6240

 

PURPOSE:

To consider approving an agreement for the Construction and Financing of Sewer Upgrades in the Southfork Peachtree model shed with AERDNA, LLC.

 

NEED/IMPACT:

AERDNA, LLC. seeks to build 50 housing units at 3563 Bishop Drive, Tucker, GA, 30084, (the “Project”) and the Project requires upgrading and expanding portions of the existing sanitary sewer infrastructure and lines to accommodate additional discharge of wastewater into the Sewer System. The purpose of this Agreement is for the parties to enter a binding contract evidencing their agreement as to the installation and financing of the improvements for this development.    The improvements will consist of upgrades and expansion of certain portions of the DeKalb County sanitary sewer infrastructure servicing the Southfork Peachtree Creek model shed. The improvements will allow for building 50 housing units at 3563 Bishop Drive, Tucker, GA, 30084. The County, through its Department of Watershed Management and/or its contractor, will determine those portions of the sanitary sewer infrastructure and lines to be upgraded and expanded (the “Work”). The improvements will be completed by March 31, 2026. Completed improvements shall generate 27,750 gallons per day in sewer capacity credits as calculated per DeKalb County’s Capacity Assurance Banking Credit Program. Company agrees that upon completion of the improvements and before Company shall be allowed access to the County’s sanitary sewer system, Company shall reimburse the County the total estimated cost of $256,500.00 for sewer improvements in the Southfork Peachtree Creek model shed. (“Company’s Contribution”).

 

FISCAL IMPACT:

The County's contribution is not anticipated to exceed $0.00

 

RECOMMENDATION:

Recommended Action

To authorize the CEO or designee to execute the Agreement and all necessary documents in a form acceptable to the County Attorney.