Title: Commission District(s): All RFP - Request for Proposal No. RFP No. 24-500674 Water Meter Installation and Cul-de-Sac Renewal Program (Annual Contract with Four (4) Options to Renew) - Option B: New Water Meter Installation Project: for use by the Department of Watershed Management (DWM). Consists of providing water meter installations, upgrades and replacements. Recommend award to the sole proposer who is responsive and responsible: Metals and Materials Engineers, LLC. Amount Not to Exceed: $12,158,975.00.
Attachments: 1. Agenda Notes, 2. UD Recommendation, 3. Cumulative Score Report for RFP No. 24-500674 Water Meter Installation and Cul-de-Sac Renewal Program (Annual Contract with Four (4) Options to Renew), 4. Market Survey, 5. RFP Evaluation Summary

Purchasing Type: Request for Proposals (RFP)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): All

RFP - Request for Proposal No. RFP No. 24-500674 Water Meter Installation and Cul-de-Sac Renewal Program (Annual Contract with Four (4) Options to Renew) - Option B: New Water Meter Installation Project: for use by the Department of Watershed Management (DWM).  Consists of providing water meter installations, upgrades and replacements. Recommend award to the sole proposer who is responsive and responsible: Metals and Materials Engineers, LLC.  Amount Not to Exceed: $12,158,975.00.

Body

 

Information Contact: Michelle Butler, Chief Procurement Officer

Phone Number: (404) 687-3581

 

PURPOSE:

Consists of providing water meter installations, upgrades, and replacements. Two (2) proposals were received-one (1) for Option A: Cul De Sac and Service Line Replacement, and one (1) for Option B: New Water Meter Installation Project. DWM has opted to award the contract to the sole proposer for Option B only, as water meter installation is a top priority. This contract will be used to meet the demand of new development by installing water meters during construction and to address the current backlog of service line renewals. DWM has decided not to request an award for Option A at this time.

 

RECOMMENDATION:

Recommended Action

Recommend award to the sole proposer who is responsive and responsible:     

 

Option B

Metals and Materials Engineers, LLC, 1669 Litton Drive, Stone Mountain, GA 30083

 

Amount Not To Exceed: $12,158,975.00

 

And authorize the CEO to execute the contract and all associated documents.

 

Evaluation Committee Scores:

 

Firms                                                                                                                              Scores

Option A                                                                                                          101.6

GS Construction, Inc.

 

Option B

Metals and Materials Engineers, LLC                      94.8

 

After evaluation of technical and cost proposal, the recommendation is to award Option B only to the sole proposer who is responsive and responsible.

 

ADDITIONAL INFORMATION:

1. LSBE Participation:                                                                                    20%

2. Contract Effective Date:                                                                                    Execution Date

3. Contract Expiration Date:                                                                                     1 Year Term with 4 Options to Renew

4. Amount Spent on Previous Contracts:                                          $25,374,661.97