File #: 2021-3056    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 8/27/2021 In control: Board of Commissioners
On agenda: 9/28/2021 Final action: 9/28/2021
Title: Commission District(s): 3 and 6 SPLOST Funding for Constitution Road Freight Corridor Operational and Safety Improvements - Phase 1
Attachments: 1. PIP 2021 Constitution Road Freight Corridor Operational & Safety Improvements

                                    

Public Hearing:  YES      NO                                                   Department: Public Works - Transportation                                     

 

SUBJECT:

Title

Commission District(s): 3 and 6

SPLOST Funding for Constitution Road Freight Corridor Operational and Safety Improvements - Phase 1

Body

 

Information Contact: David Pelton

Phone Number: 770-492-5206

 

PURPOSE:

To consider reserving $3,614,622 of SPLOST funds from line 1B - Federal and State Transportation Project Match Funds for Transportation Purposes for the Constitution Road Freight Corridor Operational and Safety Improvements - Phase 1 project;
To consider authorizing the Chief Executive Officer to execute all necessary document for completion of this project.

 

NEED/IMPACT:

The Metro South Community Improvement District (MSCID) has received a $1 million Georgia Transportation Infrastructure Bank (GTIB) grant for safety and operational improvements to the Constitution Road freight corridor.  Proposed improvements include intersection improvements and a traffic signal at the SR 42/ Bailey Street intersection and a roundabout at the Bailey St./Fayetteville Rd./Fleetwood Dr./Woodstock Rd. intersection. The project will improve access to SR 42 and I-285 for the numerous freight and truck oriented businesses in the Constitution Road area. 

 

FISCAL IMPACT:

The total estimated cost of the project is $4,814,622, with $200,000 of funding from MSCID and $1,000,000 of funding from the GTIB grant.  The proposed county contribution from SPLOST category 1B is $3,614,622.00

 

RECOMMENDATION:

Recommended Action

To reserve $3,614,622 of SPLOST funds from line 1B - Federal and State Transportation Project Match Funds for Transportation Purposes for the Constitution Road Freight Corridor Operational and Safety Improvements - Phase 1 project; and

To authorize the Chief Executive Officer to execute all necessary documents for completion of this project.