File #: 2025-0368    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 3/7/2025 In control: PWI-Public Works & Infrastructure Committee
On agenda: 4/1/2025 Final action:
Title: Commission District(s): 5 and 7 CSX Railroad Construction Phase Services for Redan Road at South Stone Mountain Lithonia Road Traffic Signal

 

Public Hearing:  YES      NO                                                   Department: Public Works - Transportation                                     

 

SUBJECT:

Title

Commission District(s): 5 and 7

CSX Railroad Construction Phase Services for Redan Road at South Stone Mountain Lithonia Road Traffic Signal

Body

 

Information Contact: David Pelton

Phone Number: 770-492-5206

 

PURPOSE:

To consider authorizing the payment of $407,823.00 to CSX Transportation, Inc. for construction phase services related to the Redan Road at South Stone Mountain Lithonia Road traffic signal project;
To consider reserving $407,823.00 of SPLOST 1 funds from line 1D - Transportation Enhancements for a new traffic signal at the Redan Road at South Stone Mountain Lithonia Road intersection; and
To consider authorizing the Chief Executive Officer to execute all necessary documents for completion of the project.

 

NEED/IMPACT:

The proposed traffic signal for Redan Road at South Stone Mountain Lithonia Road is in close proximity to a

CSX railroad crossing. As a result, CSX will need to implement changes to their crossing in order to properly

coordinate the crossing signal with the new traffic signal. The requested construction phase funds will

enable CSX to implement the needed changes.

 

FISCAL IMPACT:

$407,823.00 of Category 1D SPLOST 1 funds will be used to cover this cost. 

 

RECOMMENDATION:

Recommended Action

To authorize the payment of $407,823.00 to CSX Transportation, Inc. for construction phase services related to the Redan Road at South Stone Mountain Lithonia Road traffic signal project;

To reserve $407,823.00 of SPLOST 1 funds from line 1D - Transportation Enhancements for a new traffic signal at the Redan Road at South Stone Mountain Lithonia Road intersection; and

To authorize the Chief Executive Officer to execute all necessary documents for completion of the project.