LB - Invitation No. 20-101212 Scott Candler Water Treatment Plant - Ozone Generators Design and Installation: for use by The Department of Watershed Management (DWM). Consists of the design, installation, and the commission of two (2) ozone generators, including all supporting components, to operate in parallel with two existing generators. Recommend award to the lowest, responsive and responsible bidder: Heavy Constructors, Inc. Amount Not To Exceed $7,112.900.00.
Body
Information Contact: Cathryn G. Horner, Director
Phone Number: (404) 371-6334
PURPOSE:
Consists primarily of the provision of design services to facilitate the manufacturing of two (2) ozone generators according to specifications and the delivery and installation of those generators at the Scott Candler Water Treatment Plant. The installation of the two (2) ozone generators, will include but is not limited to: the Control Logix/Compact (PLC) change out to Allen Bradley; the connection of pipework; new power supply units, switchgear, cabling, and all instrumentation and control requirements. Lastly, services will include acceptance testing and commissioning of the new equipment with the existing equipment. Design and installation of the requested ozone generators will contribute to the continued filtration of the County's drinking water. Two (2) bids were received.
RECOMMENDATION:
Recommended Action
Recommend award to the lowest, responsive and responsible bidder:
Heavy Constructors, Inc., 1596 Lower Roswell Road, Marietta, GA 30068
Amount Not To Exceed: $7,112,900.00
and authorize the Chief Executive Officer to execute the contract and all associated documents.
ADDITIONAL INFORMATION:
1. LSBE Participation: 20.35%
2. Mentor Prot?g?: Sol Construction,...