Title: Commission District(s): ALL CO - Change Order No.1 to Contract No. 1210069 for Architecture and Engineering Services for the Renovation and Development of the 178 Sams Street Facility: for use by the Department of Facilities Management (FM). Consists of providing programming, design and construction administration services for the 178 Sams Street Facility. Awarded to Stevens & Wilkinson, GA, Inc. Amount Not To Exceed: $26,155.00.
Attachments: 1. Agenda Notes, 2. UD Change Order Request - 2021-2826, 3. Quote

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): ALL

CO - Change Order No.1 to Contract No. 1210069 for Architecture and Engineering Services for the Renovation and Development of the 178 Sams Street Facility: for use by the Department of Facilities Management (FM).  Consists of providing programming, design and construction administration services for the 178 Sams Street Facility.  Awarded to Stevens & Wilkinson, GA, Inc.  Amount Not To Exceed: $26,155.00.

Body

 

Information Contact: Cathryn G. Horner, Director

Phone Number: (404) 371-6334

 

PURPOSE:

Awarded by the BOC on May 12, 2020 for an amount not to exceed $842,922.00.  This contract consists of providing programming, design and construction administration services for the 178 Sams Street Facility.  This request is to extend the term for redesign work required in Buildings 1 and 2 and to complete construction administration. These changes include additional office space, shower and changing rooms, addition of a unisex bathroom, a meeting room, security monitoring offices and build-out of additional offices to accommodate building support staff such as IT and Human Resources. 

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 1 through March 31, 2022 with:

 

Stevens & Wilkinson, GA, Inc., 100 Peachtree St., NW, Suite 2500, Atlanta, GA 30303

 

Amount Not To Exceed: $26,155.00

 

and authorize the Chief Executive Officer to execute the change order and all associated documents.

 

ADDITIONAL INFORMATION:

1.  Contract Effective Date:                                                                May 12, 2020

2.  Contract Expiration Date:                                                               December 31, 2021

3.  Amount Spent to Date:                                                               $579,624.81

4.  Funding:                                                                                                         General Operating (FM)