File #: 2021-3219    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 10/7/2021 In control: Board of Commissioners
On agenda: 11/9/2021 Final action:
Title: Commission District(s): 4 CO - Change Order No. 2 to Contract No. 1171444 for Road Widening, Sidewalks, Bike Lanes (Rockbridge Road - Allgood to Rowland Road) - PI#s 008121/0012789: for use by Public Works - Transportation. This contract consists of the widening of Rockbridge Road from Allgood to Rowland Road to allow for the construction of sidewalks and bike lanes. Awarded to E. R. Snell Contractor, Inc. CONTRACT TERM EXTENSION ONLY.
Attachments: 1. Agenda Notes for 2021-3219, 2. UD Change Order Request - Rockbridge Road ER Snell Term Extension

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): 4

CO - Change Order No. 2 to Contract No. 1171444 for Road Widening, Sidewalks, Bike Lanes (Rockbridge Road - Allgood to Rowland Road) - PI#s 008121/0012789: for use by Public Works - Transportation.  This contract consists of the widening of Rockbridge Road from Allgood to Rowland Road to allow for the construction of sidewalks and bike lanes.  Awarded to E. R. Snell Contractor, Inc. CONTRACT TERM EXTENSION ONLY.

Body

 

Information Contact: Cathryn G. Horner, Chief Procurement Officer

Phone Number: (404) 371-6334

 

PURPOSE:

Awarded by the BOC on July 23, 2019 for an amount not to exceed $3,223,197.45.  On March 9, 2021, the BOC approved Change Order No. 1 adding funds for an amount not to exceed $26,174.72 for the lowering of two (2) sanitary sewer laterals that are in conflict with the proposed drain system and to extend the contract term.  This request is to extend the contract term for an additional six (6) months due to utility relocation delays that are having a negative impact on the contractor’s schedule.

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 2 through June 30, 2022 with:

 

E. R. Snell Contractor, Inc., 1785 Oak Road, Snellville, GA 30078

 

and authorize the Chief Executive Officer to execute the change order and all associated documents.

 

ADDITIONAL INFORMATION:

1. DBE Participation:                        14% - PI 008121/ 14% - PI 0012789

2. Contract Effective Date:                July 23, 2019

3. Contract Expiration Date:              December 31, 2021

4. Amount Spent To Date:                 $2,699,062.20

5. Funding:                                         SPLOST (Category 1B-State/Federal Match)

                                                                                               GDOT

                                                                                               DWM (Renewal & Extension)