Title: Commission District(s): 2 & 6 Georgia Department of Transportation Contract Item Agreement - Water and Sewer Facilities Project PI 0013991 State Route 42 at South Fork Peachtree Creek 3.35 miles northwest of Decatur in DeKalb County
Attachments: 1. PI 0013991 - DeKalb - DeKalb County WS - Contract Item Agm Pkg

Public Hearing: YES ? NO ? Department: Watershed Management

SUBJECT:
Title
Commission District(s): 2 & 6
Georgia Department of Transportation Contract Item Agreement - Water and Sewer Facilities Project PI 0013991 State Route 42 at South Fork Peachtree Creek 3.35 miles northwest of Decatur in DeKalb County
Body

Information Contact: Reginald Wells
Phone Number: 770-621-7208

PURPOSE:
To authorize payment to the Georgia Department of Transportation (GDOT) for the water installation/adjustments to upgrade and add safety improvements associated with the following project; and to authorize the Chief Executive Officer to execute agreement that allow for the payments and to execute all necessary documents to complete this transaction:

? PI 0013991 State Route 42 at South Fork Peachtree Creek 3.35 miles northwest of Decatur in DeKalb County estimated $861,272.78

NEED/IMPACT:
The GDOT projects P.I. No. 0013991 for the water installation/adjustments to upgrade and add safety improvements on State Route 42 at South Fork Peachtree Creek 3.35 miles northwest of Decatur in DeKalb County, Georgia. The Department of Watershed Management has existing utilities within the construction limits that are in conflict with the proposed work or need to be replaced due to age. Therefore, the County entered into a Contact Item Agreement with GDOT to include installations/adjustments for the State Route 42 at South Fork Peachtree Creek 3.35 miles northwest of Decatur project to prevent construction delays, minimized impact to adjacent property owners and the traveling public. The County must agree to pay the estimated cost of completing the work; the exact payment amount will be based on unit bid prices.

FISCAL IMPACT:
Schedule Delay - Resulting in delay claims
Change in scope (rework) - Impacts to budget due to possible design and field changes

RECOMMENDATION:
Recommended Action
To authorize the chief executiv...