Purchasing Type: Change Order (CO)
Public Hearing: YES ? NO ? Department: Purchasing & Contracting
AGENDA ITEM:
Title
Commission District(s): All
CO - Change Order No. 2 to Contract No. 1381109 Design/Build Services for Snapfinger Advanced Wastewater Treatment Facility (SFAWTF) Expansion - Phase 3B Project (UV Disinfection System): For use by the Department of Watershed Management (DWM) to obtain design services, furnishing, permitting and constructing of UV system. Seeking to increase contract scope of work, funding and performance time. Awarded to Morgan Contracting, Inc. Amount Not to Exceed $394,309.31.
Body
Information Contact: Michelle Butler, Chief Procurement Officer
Phone Number: (404) 687-3581
PURPOSE:
Awarded by the BOC on June 11, 2024, for an amount not to exceed $4,922,500.00. On January 13, 2026, the BOC approved Change Order No. 1 to increase the scope of work and funding in an amount not to exceed $1,413,311.17. Change Order No. 2 is being requested to provide additional funding and performance time for instrumentation and replacement of Ultraviolet effluent gate actuators and controls communication along with associated design engineering cost at Snapfinger Advanced Wastewater Treatment Facility (SFAWTF).
The implementation of a Ultraviolet Disinfection System will allow for the retiring of the hazardous gaseous chlorine disinfection process and provide the County significant health and safety benefits, while remaining compliant with the Consent Decree requirements.
RECOMMENDATION:
Recommended Action
Recommend approval of Change Order No. 2 with:
Morgan Contracting, Inc., 4124 Flakes Mill Road, Decatur, GA 30034
Amount Not to Exceed: $394,309.31.
and authorize the Chief Executive Officer to execute the change order and all associated documents.
ADDITIONAL INFORMATION:
1. LSBE Participation: 20%
2. Contract Effective Date: February 14, 2025
3...
Click here for full text