Purchasing Type: Change Order (CO)
Public Hearing: YES ☐ NO ☒ Department: Purchasing & Contracting
AGENDA ITEM:
Title
Commission District(s): All
CO - Change Order No. 2 to Contract No. 1294325 Ozone Generation Support (Three (3) Year Multiyear Contract). For use by the Department of Watershed Management to obtain professional maintenance, repair and replacement services for Scott Candler Water Treatment Plant ozone generation systems. Seeking increase to contract funds and term through June 30, 2027. Awarded to Telchine Energy Technologies, LLC. Amount Not To Exceed: $100,000.00.
Body
Information Contact: Michelle Butler, Chief Procurement Officer
Phone Number: (404) 687-3581
PURPOSE:
Awarded by the BOC on June 14, 2022, for an amount not to exceed $379,200.00. On May 6, 2025, the BOC approved Change Order No. 1 to increase the contract term through December 31, 2026. No additional funds were added. This contract consists of providing professional maintenance, repair and replacement services for ozone generation systems at Scott Candler Water Treatment Plant. This request seeks to increase the contract funds and term through June 30, 2027, for an amount not to exceed $100,000.00. This will allow services to continue while the re-solicitation process is completed.
RECOMMENDATION:
Recommended Action
Recommend approval of Change Order No. 2 with:
Telchine Energy Technologies, LLC, 8780 125th Ave. Suite B, Largo, FL 33773
Amount Not To Exceed: $100,000.00
ADDITIONAL INFORMATION:
1. Contract Effective Date: June 28, 2022
2. Contract Expiration Date: December 31, 2026
3. Amount Spent to Date: $362,962.83
4. Funding: Enterprise - Operating (DWM)