Title: Commission District(s): ALL CO - Change Order No. 2 to Contract No. 1379287, Juvenile Justice Center Canopy Installation (180 Day Contract): for use by the Department of Facilities Management (FM). This contract consists of construction services for the installation of a canopy over the Judges' parking lot at the DeKalb County Juvenile Justice Center. This request seeks to increase the contract term through August 31, 2025. Awarded to: Brad Construction Company II, LLC. CONTRACT TERM INCREASE ONLY
Attachments: 1. 2025-0596, Agenda Notes, 2. 2025-0596 UD Change Order Request Form

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): ALL

CO - Change Order No. 2 to Contract No. 1379287, Juvenile Justice Center Canopy Installation (180 Day Contract): for use by the Department of Facilities Management (FM). This contract consists of construction services for the installation of a canopy over the Judges’ parking lot at the DeKalb County Juvenile Justice Center. This request seeks to increase the contract term through August 31, 2025. Awarded to: Brad Construction Company II, LLC. CONTRACT TERM INCREASE ONLY

Body

 

Information Contact: Michelle Butler, Chief Procurement Officer

Phone Number: (404) 687-3581

 

PURPOSE:

Awarded by the BOC, on May 28, 2024 for an amount not to exceed $443,831.19.  On October 8, 2024, the BOC approved Change Order No. 1 notating a revised contract term of May 31, 2025 to allow the vendor appropriate time to complete from the recission and re-award of this project.  This contract consists of the installation of a canopy over the Judges’ parking lot at the DeKalb County Juvenile Justice Center. This request seeks to increase the contract term through August 31, 2025 due to delays in the manufacturing of the pre-fabricated building.

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 2 with:

 

Brad Construction Company II, LLC, 500 W. Lanier Ave., Fayetteville, GA 30214

 

and authorize the Chief Executive Officer to execute the change order and all associated documents.

 

ADDITIONAL INFORMATION:

1. LSBE Participation                                                               LSBE-MSA Firm

2. Contract Effective Date:                                          September 19, 2024

3. Contract Expiration Date:                                          May 31, 2025

4. Amount Spent To Date:                                          $97,158.63