File #: 2018-2195    Version: 1 Name:
Type: Resolution Status: Action
File created: 6/4/2018 In control: Board of Commissioners
On agenda: 11/13/2018 Final action: 11/13/2018
Title: Commission District(s): 3 & 7 CO - Change Order No. 1 to Contract No. 972548 Snapfinger Advanced Wastewater Treatment Facilities Expansion - Phase 2: for use by the Department of Watershed Management (DWM). This contract consists of the phase 2 expansion to the Snapfinger Advanced Wastewater Treatment Facility; inclusive of site preparation, modification of existing structures, and the construction of new structures. This request is to extend the contract term and to increase the funding to allow for completion of eight (8) proposed design and construction changes. Awarded to Archer Western Construction, LLC. Amount Not To Exceed $350,000.00.
Attachments: 1. Agenda Notes, 2. 2018-2195 UD Change Request No. 1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
11/13/20181 Board of Commissioners    Not available Meeting details Video Video
11/5/20181 PWI-Public Works & Infrastructure Committee recommended for approval.Pass Action details Meeting details Not available
11/5/20181 Board of Commissioners deferred to the next meetingPass Action details Meeting details Video Video
10/9/20181 Board of Commissioners deferred.Pass Action details Meeting details Not available
10/9/20181 Board of Commissioners approved  Action details Meeting details Video Video
9/18/20181 PWI-Public Works & Infrastructure Committee recommended for approval.Pass Action details Meeting details Not available
9/4/20181 PWI-Public Works & Infrastructure Committee recommended holding in committee  Action details Meeting details Not available
8/28/20181 Board of Commissioners    Not available Meeting details Video Video
8/21/20181 PWI-Public Works & Infrastructure Committee recommended holding in committee  Action details Meeting details Not available
7/24/20181 Board of Commissioners deferred 30 daysPass Action details Meeting details Video Video
7/17/20181 PWI-Public Works & Infrastructure Committee recommended holding in committee  Action details Meeting details Not available
7/10/20181 Board of Commissioners deferredPass Action details Meeting details Video Video
6/28/20181 PWI-Public Works & Infrastructure Committee recommended holding in committee  Action details Meeting details Not available
6/26/20181 Board of Commissioners deferred.Pass Action details Meeting details Video Video
6/19/20181 Committee of the Whole    Not available Meeting details Not available
6/19/20181 PWI-Public Works & Infrastructure Committee recommended for deferralPass Action details Meeting details Not available
Purchasing Type: Change Order (CO)
Public Hearing: YES ? NO ? Department: Purchasing & Contracting

AGENDA ITEM:
Title
Commission District(s): 3 & 7
CO - Change Order No. 1 to Contract No. 972548 Snapfinger Advanced Wastewater Treatment Facilities Expansion - Phase 2: for use by the Department of Watershed Management (DWM). This contract consists of the phase 2 expansion to the Snapfinger Advanced Wastewater Treatment Facility; inclusive of site preparation, modification of existing structures, and the construction of new structures. This request is to extend the contract term and to increase the funding to allow for completion of eight (8) proposed design and construction changes. Awarded to Archer Western Construction, LLC. Amount Not To Exceed $350,000.00.

Body
Information Contact: Talisa Clark, CPPO
Phone Number: (404) 687-2797

PURPOSE:
Awarded by the BOC on June 9, 2015 for an amount not to exceed $187,869,380.00. This contract consists of blasting and clearing of rock; construction of a retaining wall; demolition of existing tankage and equipment; construction of the new headwork, biological reactors, membrane bio-reactors (MBR), chemical storage and feed facilities; and modifications to the chlorine contact basin, sludge dewatering, sludge holding tank, and odor control units. This request is to extend the contract term to December 31, 2020 and to increase the funding to allow for completion of eight (8) proposed design and construction changes.

RECOMMENDATION:
Recommend approval of Change Order No. 1 with:

Archer Western Construction, LLC, 2410 Paces Ferry Road, Suite 600, Atlanta, GA 30339

Amount Not To Exceed: $350,000.00

Recommended Action
and authorize the Chief Executive Officer to execute the change order and all associated documents

ADDITIONAL INFORMATION:
1. LSBE Participation: 15.14%
2. Contract Effective Date: August 5, 2015
3. Contract Expirat...