File #: 2017-0784    Version: 1 Name:
Type: Resolution Status: Passed
File created: 8/9/2017 In control: Board of Commissioners
On agenda: 9/12/2017 Final action: 9/14/2017
Title: Commission District(s): 2 & 6 Transfer of Funds to the Coventry Road Quiet Zone Project Cost to County: $240,413

                                    

Public Hearing:  YES      NO                                                   Department: Public Works - Transportation                                     

 

SUBJECT:

Title

Commission District(s): 2 & 6

Transfer of Funds to the Coventry Road Quiet Zone Project

Cost to County: $240,413

Body

Information Contact: David Pelton

Phone Number: 770-492-5206

 

PURPOSE:

To consider transferring $60,000.00 from Project 100121, Award 601574 to Project 104437 for the Coventry Road Quiet Zone project; and
To consider authorizing the payment of $240,143.00 to CSX Transportation for the construction of new gates at the Coventry Road railroad crossing; and
To consider authorizing the Chief Executive Officer to execute all necessary documents for completion of the
project.

 

NEED/IMPACT:

The proposed transfer will move some of the remaining county funds from the completed South Fork Peachtree Creek Trail Phase IV project to complete funding for the Coventry Road Quiet Zone project.  The addition of two gates will make the crossing eligible for quiet zone designation.  The Board of Commissioners previously authorized another transfer of funds to the Coventry Road Quiet Zone project on July 12, 2016.

 

FISCAL IMPACT:

The proposed gates will have a cost to the county of $240,413.00.

 

RECOMMENDATION:

Recommended Action

To transfer $60,000.00 from Project 100121, Award 601574 to Project 104437 for the Coventry Road Quiet Zone project; and

To authorize the payment of $240,413.00 to CSX Transportation for the construction of new gates at the Coventry Road railroad crossing; and

To authorize the Chief Executive Officer to execute all necessary documents for completion of the project.