File #: 2020-0337    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 3/5/2020 In control: Board of Commissioners
On agenda: 4/14/2020 Final action: 4/14/2020
Title: Commission District(s): 2 and 6 Georgia Power Relocation Costs for Briarcliff Road Sidewalk

                                    

Public Hearing:  YES      NO                                                   Department: Public Works - Transportation                                     

 

SUBJECT:

Title

Commission District(s): 2 and 6

Georgia Power Relocation Costs for Briarcliff Road Sidewalk

Body

 

Information Contact: David Pelton

Phone Number: 770-492-5206

 

PURPOSE:

To consider authorizing the payment of $87,134.00 to Georgia Power for relocation of overhead power lines for construction of sidewalk on Briarcliff Road from north of Clifton Road to Briar Vista Terrace; and
To consider appropriating $1,528.00 of SPLOST funds from item 1C - Pedestrian Improvements to fund a portion of this cost; and
To consider authorizing the Chief Executive Officer to execute all necessary documents pertaining to this project.

 

NEED/IMPACT:

Georgia Power will need to relocate distribution lines in order for DeKalb County to construct sidewalk along the east side of Briarcliff Road from north of Clifton Road to Briar Vista Terrace. This was a high rated project in the February 2020 SPLOST Sidewalk Prioritization.

 

FISCAL IMPACT:

Remaining 2016 Bond Re-funding funds for this project will cover $85,606.00 of the Georgia Power cost.  The remaining $1,528.00 is proposed to be paid using SPLOST funds from item 1C - Pedestrian Improvements.

 

RECOMMENDATION:

Recommended Action

To authorize the payment of $87,134.00 to Georgia Power for relocation of overhead power lines for construction of sidewalk on Briarcliff Road from north of Clifton Road  to Briar Vista Terrace; and

To appropriate $1,528.00 of SPLOST funds from item 1C - Pedestrian Improvements to fund a portion of this cost; and

To authorize the Chief Executive Officer to execute all necessary documents pertaining to this project.