File #: 2020-1491    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 11/17/2020 In control: Board of Commissioners
On agenda: 12/8/2020 Final action:
Title: Commission District(s): 1 and 7 CO - Change Order No. 1 to Contract No. 1187912 for Hugh Howell Road Sidewalk from Lawrenceville Highway to Tucker Industrial Road (120 days): for use by Public Works-Transportation. This contract consists of the construction of a sidewalk alongside Hugh Howell Road from Lawrenceville Highway to Tucker Industrial Road. Awarded to Construction 57, Incorporated. Amount Not To Exceed: $8,288.27.
Attachments: 1. AGENDA NOTES - 2020-1491, 2. CO1 Hugh Howell Sidewalk revised-signed - 2020-1491

Purchasing Type: Change Order (CO)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): 1 and 7

CO - Change Order No. 1 to Contract No. 1187912 for Hugh Howell Road Sidewalk from Lawrenceville Highway to Tucker Industrial Road (120 days): for use by Public Works-Transportation. This contract consists of the construction of a sidewalk alongside Hugh Howell Road from Lawrenceville Highway to Tucker Industrial Road.  Awarded to Construction 57, Incorporated.  Amount Not To Exceed: $8,288.27.

Body

 

Information Contact: Cathryn G. Horner, Director

Phone Number: (404) 371-6334

 

PURPOSE:

Awarded by the BOC on November 12, 2019 for an amount not to exceed $200,605.25.  This request is to add funding to cover the cost of increased quantities in the number of handrails, sodding, repair to existing sidewalk ramp and a catch basin.

 

RECOMMENDATION:

Recommended Action

Recommend approval of Change Order No. 1 with:

 

Construction 57, Incorporated, 809 Park North Boulevard, Clarkston, GA 30021

 

Amount Not To Exceed: $8,288.27

 

and authorize the Chief Executive Officer to execute the change order and all associated documents.

 

ADDITIONAL INFORMATION:

1. Contract Effective Date:                                 November 12, 2019

2. Contract Expiration Date:                               December 31, 2020

3. Amount Spent To Date:                                  $165,642.12

4. Funding:                                                          CDBG 2016 (CD)