File #: 2021-2183    Version: 1 Name:
Type: Resolution Status: Action
File created: 2/8/2021 In control: Board of Commissioners
On agenda: 3/23/2021 Final action:
Title: Commission District(s): All CO - Change Order No. 3 to Contract No. 1177081 Trenchless Sewer Line Rehabilitation and Construction and Televising Inspection Services (Savannah Contract: Event No. 5937/Buyer Contract No. 886 [DeKalb Cooperative Agreement]: for use by Department of Watershed Management (DWM). This contract is a cooperative agreement and consists of providing sewer line rehabilitation services; to include inspections, sewer line cleaning, and cured in place pipe. This request is to increase the scope of work, contract term through December 31, 2021, and funding. This request will allow for additional services and the continuation of existing sanitary sewer line rehabilitation services. Amount Not to Exceed: $14,674,232.75. Awarded to Insituform Technologies, LLC.
Attachments: 1. 2021 03.23 Item 2021-2183, 2. 2021-2183 Agenda Notes, 3. 2021-2183 UD Change Order Request No. 3
Substitute
Purchasing Type: Change Order (CO)
Public Hearing: YES ? NO ? Department: Purchasing & Contracting

AGENDA ITEM:
Title
Commission District(s): All
CO - Change Order No. 3 to Contract No. 1177081 Trenchless Sewer Line Rehabilitation and Construction and Televising Inspection Services (Savannah Contract: Event No. 5937/Buyer Contract No. 886 [DeKalb Cooperative Agreement]: for use by Department of Watershed Management (DWM). This contract is a cooperative agreement and consists of providing sewer line rehabilitation services; to include inspections, sewer line cleaning, and cured in place pipe. This request is to increase the scope of work, contract term through December 31, 2021, and funding. This request will allow for additional services and the continuation of existing sanitary sewer line rehabilitation services. Amount Not to Exceed: $14,674,232.75. Awarded to Insituform Technologies, LLC.

Body
Information Contact: Cathryn G. Horner, Director
Phone Number: (404) 371 - 6334

PURPOSE:
Awarded by the BOC on August 13, 2019 for an amount not to exceed $15,681,161.35. On July 28, 2020, the BOC approved Change Order No. 1 to increase funding in an amount not to exceed $437,591.60. On December 8, 2020, the BOC approved Change Order No. 2 to increase scope of work and contract term to September 30, 2021. This contract consists of cooperatively purchasing from the competitively let City of Savannah annual contract for the provision of trenchless sewer rehabilitation services. This request will continue in the progress of completing needed sanitary sewer line rehabilitation around the County.

RECOMMENDATION:
Recommended Action
Recommend approval of Change Order No. 3 with:

Insituform Technologies, LLC, 17988 Edison Avenue, Chesterfield, Missouri 63005

Amount Not to Exceed: $14,674,232.75

and authorize the Chief Executive Officer to execute the amendment and all as...

Click here for full text