File #: 2022-1969    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 7/25/2022 In control: Board of Commissioners
On agenda: 8/23/2022 Final action: 8/23/2022
Title: Commission District(s): 3 & 6 Agreement for the Construction and Financing of Sewer Upgrades with Aurora Senior I, LP Not to Exceed $72,500.
Attachments: 1. 3101 Clifton Springs - Aurora Senior Agreement agenda (003)

Public Hearing: YES ? NO ? Department: Watershed Management

SUBJECT:
Title
Commission District(s): 3 & 6
Agreement for the Construction and Financing of Sewer Upgrades with Aurora Senior I, LP Not to Exceed $72,500.
Body

Information Contact: David Hayes, Director
Phone Number: 770-414-6240

PURPOSE:
To consider approving an agreement for the Construction and Financing of Sewer Upgrades in
the Snapfinger model shed with Aurora Senior I, LP.

NEED/IMPACT:
Aurora Senior I, LP seeks to enhance the community by constructing 138 Senior Housing Units at 3101 Clifton Springs Road, Decatur, GA 30034, (the "Project") and the Project requires upgrading and expanding portions of the existing sanitary sewer infrastructure and lines to accommodate additional discharge of wastewater into the Sewer System. The purpose of this Agreement is for the parties to enter a binding contract evidencing their agreement as to the installation and financing of the improvements for this development. This development will enhance its surrounding community as per section 3 of the County policy for allocating wastewater capacity credits, hence allowing the company to participate in the completion of capacity credit generation. The improvements will consist of upgrades and expansion of certain portions of the DeKalb County sanitary sewer infrastructure and lines servicing the Snapfinger model shed. The improvements will allow for a total of 138 residences. The County, through its Department of Watershed Management and/or its contractor, will determine those portions of the sanitary sewer infrastructure and lines to be upgraded and expanded (the "Work"). The Work will be completed by June 1, 2023. Completed improvements shall generate 36,768 gallons per day in sewer capacity credits as calculated per DeKalb County's Capacity Assurance Banking Credit Program. Company agrees that upon completion of the improvements and before...

Click here for full text