File #: 2022-2194    Version: 1 Name:
Type: Resolution Status: Action
File created: 9/14/2022 In control: Board of Commissioners
On agenda: 10/25/2022 Final action:
Title: Commission District(s): 1 & 6 Change Order to Agenda Item 2020-0964 Georgetown Gateway project for City of Dunwoody CS 5156/Chamblee Dunwoody Road from Cotillion Drive to Peeler Road for additional $10,477.50
Attachments: 1. PI No. 0012875 City of Dunwoody Change Order

                                    

Public Hearing:  YES      NO                                                   Department: Watershed Management                                     

 

SUBJECT:

Title

Commission District(s): 1 & 6

Change Order to Agenda Item 2020-0964 Georgetown Gateway project for City of Dunwoody CS 5156/Chamblee Dunwoody Road from Cotillion Drive to Peeler Road for additional $10,477.50

Body

 

Information Contact: David Hayes

Phone Number: 770-414-6240

 

PURPOSE:

DWM is requesting additional funding to the City of Dunwoody project under the approved Intergovernmental Agreement (IGA) for the Georgetown Gateway project for City of Dunwoody CS 5156/Chamblee Dunwoody Road from Cotillion Drive to Peeler Road improvements that are associated with Watershed Management in the amount of $10,477.50.  City of Dunwoody original quote submitted for DWM portion being $566,777.20 however Lewallen submitted a change to City of Dunwoody in the amount of $10,477.50 bringing the final cost to $577,254.70 for Georgetown Gateway project for City of Dunwoody CS 5156/Chamblee Dunwoody Road from Cotillion Drive to Peeler Road improvements

 

NEED/IMPACT:

The County has agreed to pay the cost of completing the work the City of Dunwoody project for Georgetown Gateway project for City of Dunwoody CS 5156/Chamblee Dunwoody Road from Cotillion Drive to Peeler Road improvements. This will ensure that there are adequate funds on this agreement to enable the contractor to continue working on our water and sewer installation/adjustments.

 

FISCAL IMPACT:

Schedule Delay - Resulting in delay claims

 

RECOMMENDATION:

Recommended Action

Request approval for the change to agenda 2020-0964 in the amount of $10,477.50 to make the project total cost of $577.254.70 to be paid from Watershed Renewal & Extension(R&E) and to authorize the Chief Executive Officer to execute an agreement allowing for these payments and to execute all necessary documents for City of Dunwoody to complete these transactions associated with the Georgetown Gateway project for City of Dunwoody CS 5156/Chamblee Dunwoody Road from Cotillion Drive to Peeler Road.