File #: 2023-0201    Version: 1 Name:
Type: Resolution Status: Preliminary Item
File created: 1/30/2023 In control: Board of Commissioners
On agenda: 2/28/2023 Final action:
Title: Commission District(s): All REN - Contract Nos. 1242005 and 1242006 Electrical Switchgear Inspections and Repair (Annual Contract - 2nd Renewal of 2 Options to Renew): for use by the Department of Watershed Management (DWM). The contracts consist of providing inspection and repair of switchgear equipment at water and wastewater treatment plants. This request seeks to ratify a previously provided sixty (60) day contract term increase and exercise the 2nd renewal option through January 31, 2024 for both contracts. Awarded to Cleveland Electric Company and Brown Electrical Services, LLC. Total Amount Not To Exceed: $2,493,572.00
Attachments: 1. Agenda Notes, 2. Contract Renewal Form

Purchasing Type: Renewal (REN)                               

Public Hearing:  YES      NO                                   Department: Purchasing & Contracting                                     

 

AGENDA ITEM:

Title

Commission District(s): All

REN - Contract Nos. 1242005 and 1242006 Electrical Switchgear Inspections and Repair (Annual Contract - 2nd Renewal of 2 Options to Renew): for use by the Department of Watershed Management (DWM). The contracts consist of providing inspection and repair of switchgear equipment at water and wastewater treatment plants. This request seeks to ratify a previously provided sixty (60) day contract term increase and exercise the 2nd renewal option through January 31, 2024 for both contracts. Awarded to Cleveland Electric Company and Brown Electrical Services, LLC. Total Amount Not To Exceed: $2,493,572.00

Body

 

Information Contact: Michelle Butler, Procurement Manager

Phone Number: (404) 687-3581

 

PURPOSE:

Awarded by the BOC on January 19, 2021, for a total amount not to exceed $1,854,000.00. On January 11, 2022, the BOC approved the 1st renewal for a total amount not to exceed $1,925,000.00. The contracts consist of providing inspection and repair of switchgear equipment at water and wastewater treatment plants.

This request seeks to ratify a previously provided sixty (60) day contract term increase, effective as of January 31, 2023, for both contracts. This request also seeks to exercise the 2nd renewal option through January 31, 2024.

 

RECOMMENDATION:

Recommended Action

Recommend approval to exercise the 2nd renewal option with:

 

Cleveland Electric Company, 1282 Fulton Industrial Boulevard, Atlanta, GA 30336

Estimated Amount: $2,154,918.00

 

Brown Electrical Services, LLC, 4674 Clark Howell Highway, Suite 5, Atlanta, GA 30349

Note: LSBE - MSA Firm

Estimated Amount: $338,654.00

 

Total Amount Not To Exceed: $2,493,572.00

 

ADDITIONAL INFORMATION:

1. Contract Effective Date:                                                               January 19, 2021

2. Contract Expiration Date:                                                               March 31, 2023

3. Amount Spent To Date:                                                               $1,471,427.19

4. Funding:                                                                                                         General - Operating (DWM)